Bayview Bridge Replacement

Le contenu suivant est seulement disponible en anglais.

Work to replace the Bayview Bridge will start on Monday, April 25.

A temporary bridge will be constructed adjacent to the existing bridge. Two-lane traffic will be maintained for all traffic on Route 6 during construction of the temporary bridge.

The temporary bridge will have two lanes and will also have a separate lane for pedestrians and cyclists. 

Motorists are advised to use caution entering and driving through the site. 

Target date for temporary bridge open to all traffic: July 2022.

Target date for new bridge open to all traffic: January 2023.

image of a road map

 

Media contact:
April Gallant
Department of Transportation and Infrastructure
aldgallant@gov.pe.ca

Dernière mise à jour

vendredi 22 Avril 2022, 11 h 20

Renseignements généraux

Communiquez avec le gouvernement ou cliquez sur l’onglet Commentaires pour transmettre de vos commentaires.