The Prince Edward Island Broadband Fund provides a contribution of up to 50 per cent of the eligible costs for the installation of an approved infrastructure project for enhanced broadband services. The objective of the fund is to work with Internet Service Providers (ISP), businesses and communities to provide solutions for better Internet access in the province, with a focus on rural PEI.

Approved Projects

Project Stream PEIBF Contribution Total Project Costs Project Details
Internet Service Provider $1,150,082 $3,899,165 Here
Accelerated ISP Pilot $604,675 $771,291 Here
Business $79,569 $159,138 Here
Community $640,583 $1,262,908 Here
Project Stream Total Amount  Project Details
Residential Pilot 2020-2021 $1,498,656

Projects: 568

Residential 2021-2022     $749,008 Projects: 464
Residential 2022-2023 $2,022,070 Projects: 1253
Residential 2023-2024 $535,717 Projects: 514

Back to top 

 

Internet Service Provider

Recipient PEIBF Contribution Total Project Cost Deliverable
Air Tech Communications $37,700 $75,400 Improved Internet service and coverage in the Richmond, Southwest Lot 16 and Grand River area. The project will deliver improved back-haul capacity and greater reach. Existing and new subscribers will benefit from this project.
Island Telecom Union Rd $42,262.50 $84,525.00 Install underground fibre in the Union Road area between Brackley Point Road and Horne Cross Road.
Island Telecom Services Inc. $32,120.40 $64,240.80 Upgrade Internet service and coverage in the Long River area, including improved back-haul capacity to the Darnley and Toronto areas and remedial work to the tower at the Long River site. New subscribers will benefit from this project.
Bell $1,038,000 $3,675,000 Expanded service to allow 800 new civic addresses to connect to FTTP.

Back to top

 

Accelerated ISP Stream:

Recipient PEIBF Contribution Total Project Cost Deliverable
Air Tech Communications $150,000 $216,325 Install fibre to three key serving customers in the Richmond, Grand River, Sunny Side, Arlington and Birch Hill areas.
PEI Monitoring $150,000 $180,259 Upgrade equipment on existing towers to provide service to residents in the Wood Islands, Pinette, and Southern Kings area.
Red Sands $150,000 $174,462 Install/replace two towers at Toronto Road and Springbrook to offer upgraded and expanded service to approx. 250 subscribers.
Wicked EH? $114,859 $154,005 Upgrade current equipment and materials on Charlottetown and Summerville towers to offer enhanced service to approx. 400 subscribers.
Buzz Network $39,816 $46,240 Provide wireless service to residents in the Lot 16, Wellington, Abrams Village, Cape Edgmont and Mt.Carmel area.

Back to top
 

Business Stream

Recipient PEIBF Contribution Total Project Cost Deliverable
Eastern Fabricators $7,514 $15,029 Install Bell fibre services to meet immediate and future needs of the company from its location at 341 Georgetown Road, Route 3.
Granville Ridge Consulting $7,632.94 $15,265.88 Purchase and Install a tower to provide fixed wireless service.
H6 PEI Investments $462.50

$925.00

Undertake a wireless point-to-point feed for H6 to improve service to the remote end location at 2466 Trout River Road.
BCD Automation $2,747.75 $5,495.50 Purchase and install a 50 foot tower for the wireless broadband high-speed internet.
Twin Shores $38,873.16 $77,746.32 Install a fibre feed to Twin Shores Campground.
Carruthers Farm $3,674.91 $7,349.82 P2P wireless technology to provide high speed internet to the main property and to bridge the internet connection to the other business buildings
Monaghan Farms $2,150 $4,300 Support a point to point connection to extend the current internet feed from the seed facility, over to the office building.
By the Water Shellfish $3,075 $6,150 Extended service and a dedicated static IP
Argyle Shores

$1,500

$3,000 Point to point wireless connection to Argyle Shore business.
Oyster Cove Farms $430 $860 Wireless bridge installed to provide signal to the office location.
Raspberry Point Oysters $3,075 $6,150 Plant aerial extension, fibre installed to location.
West Point Lighthouse $5,000 $10,000 Wireless bridge installed and multipoint wi-fi access equipment.
H.F Stewart $400 $800 Installation of low orbit satellite.
Olde Town Orchard $2,150 $4,300 Purchase and Install of 60’ hydro pole to access wireless high speed broadband internet.
Friends of Elmira $412 $824 Installation of low orbit satellite.
Choice Point Coaching $475 $950 Fibre extension and installation to the location.

Back to top

Community Stream

Recipient PEIBF Contribution Total Project Cost Deliverable
St. Peters Campground $5,500 $11,000.00 Upgrade the internet feed into the St. Peters Campground. This campground is operated by the Rural Municipality of St. Peters and has 85 full service sites and 10 tent sites.
Fortune Community Centre $66,825 $133,650 Extend fibre to cover 40 homes in the Fortune area.
Kingston    $568,258      $1,118,258   Extend fibre to cover 283 homes in the Kingston and surrounding areas.

Back to top 

Published date: 
September 23, 2022
Workforce, Advanced Learning and Population

General Inquiries

Economic and Population Growth
176 Great George Street
Charlottetown, PE C1A 4K7
 
Phone: 902-368-5540
Fax: 902-894-0342

DeptWALP@gov.pe.ca