Tie - Bagnall'S Pond (Hunter River) Bridge Structure Replacement (District 18)

Le contenu suivant est seulement disponible en anglais.
Numéro d’appel d’offres: 
4375
Date de publication: 
lundi 3 Août 2015
Date de fermeture: 
jeudi 20 Août 2015, 11 h 00
Type d’appel d’offres: 
Avis d’appel d’offres (AAO)
Type d’entente: 
Appel d’offres ouvert (AOO)
Valeur estimative: 
Non déterminée
Notes: 

The scope of this work includes, but is not necessarily limited to the following: the supply of all labour,
equipment, and materials necessary to completely replace the existing bridge structure with a new
bridge structure. The work on this project shall consist of traffic control; excavation; slope protection;
environmental controls; stream containment; cold plane and stockpile asphalt; reclaimed asphalt
placement and maintenance; demolition and removal of existing structure; concrete formwork and
accessories; concrete reinforcement; pre-cast concrete; pre-cast concrete structure installation; precast
concrete retaining wall; rip rap; gabion baskets; temporary box culvert bridge and bypass road
within the site; temporary traffic lane road setup and maintenance; sanitary sewer; storm sewer; road
work complete with asphalt paving; and all other ancillaries required to completely install the structure
to the satisfaction of the Owner.

TENDER CLOSES:
Thursday, 20 August 2015, 2:00 PM
11 Kent Street, 3rd Floor Jones Bldg, Charlottetown, PEI

Organisme: 
Transports et Infrastructure

Personne-ressource de l’organisme:

Carrie Adams
Téléphone: 
(902) 368-5180
Télécopieur: 
(902) 368-5425
Document de la demande de prix: