TIE CAIRNS RD BRIDGE REPLACEMENT (DISTRICT 19)
CAIRNS ROAD BRIDGE - STRUCTURE REPLACEMENT DISTRICT 19
The scope of this work includes, but is not necessarily limited to the following: the supply of all labour,
equipment, and materials necessary to completely replace the existing bridge structure with a new
bridge structure. The work on this project shall consist of but not limited to: excavation; slope
protection; environmental controls; asphalt excavation; cold plane and stockpile asphalt; stream
diversion; demolition and removal of existing structure; concrete formwork and accessories; concrete
reinforcement; precast concrete; precast concrete structure installation; waterproofing membrane;
structural steel barrier; precast concrete retaining wall; rip rap; road work complete with asphalt paving;
and all other ancillaries required to completely install the structure to the satisfaction of the Owner.